The Excavation Time Calculator is a handy tool designed to estimate the time required to complete an excavation project. By inputting values such as the excavation volume, equipment productivity rate, and working hours per day, this calculator provides an accurate estimate of the total time needed, helping users efficiently plan and manage excavation tasks.
What Does the Excavation Time Calculator Do?
The Excavation Time Calculator takes the following inputs:
- Excavation Volume (m³): The total volume of soil or material to be excavated.
- Excavation Rate (m³/hour): The rate at which the machine or equipment excavates per hour.
- Cost per Hour ($): The cost of operating the excavation equipment per hour.
Outputs:
- Excavation Time: The total time required to complete the excavation.
- Total Cost: The overall cost of the excavation process.
Formula for Excavation Time
The formula to calculate the Excavation Time is:
Excavation Time=Excavation RateExcavation Volume
Where:
- Excavation Volume = Total material to be excavated (in cubic meters, m³).
- Excavation Rate = Rate of excavation per hour (m³/hour).
Formula for Total Cost
Once the excavation time is calculated, the Total Cost can be determined using the formula:
Total Cost=Excavation Time (hours)×Cost per Hour ($)
Where:
- Excavation Time = Time calculated from the previous formula (in hours).
- Cost per Hour = Operating cost of the excavation equipment (in dollars per hour).
Example Calculation
Let’s assume the following values:
- Excavation Volume: 300 m³
- Excavation Rate: 50 m³/hour
- Cost per Hour: $100
Step 1: Calculate Excavation Time
Using the formula:
Excavation Time=Excavation RateExcavation Volume
Substitute the values:
Excavation Time=50300=6hours
Step 2: Calculate Total Cost
Now calculate the total cost using the formula:
Total Cost=Excavation Time×Cost per Hour
Substitute the values:
Total Cost=6×100=600$
Final Results:
- Excavation Time: 6 hours
- Total Cost: $600
FAQ
What is excavation rate?
Excavation rate refers to the speed or volume of earth or rock material removed per unit of time during excavation work. It's typically measured in cubic meters per hour (m³/hr) or cubic yards per hour (yd³/hr).
Check out 2 similar Excavation Time Calculator :